El Borma Field
SMIP has been awarded the contract from SITEP B.V to make a "Long Production Test" to EL BORMA # 406 well.
EL BORMA#406 well is located in EL BORMA Concession, about 30 km of EL BORMA process facilities.
The scope of work has been:
- Site survey
- Project Management
- Engineering ( Basic, FEED and Detailed Engineering )
- Technical documentation for local Authorities
- Hazop Analysis
- Supply of materials, equipments and Control System
- Construction and installation
- Mechanical work
- Piping work
- Instruments and control system installation
- Electrical installation
- Heat treatment and N.D.T
- Painting, insulation and lining
- Plant pre-commissioning, commissioning and start-up
- Operating and maintenance manual
- Plant operating and maintenance