SMIP performed the pre-commissioning, commissioning and start up of ENNAGA CPF field in Libya (station for 20 000 BOPD) with high concentration on H2S.
Customer: |
IPLL Libya ( N.O.C & PETROCANADA ) |
Project: |
Central Process Facility ( 20 000 bopd with an option for 29 000 bopd ) |
Schedule: |
12 Months |
Contract type: |
E.P.C |
Value: |
MM US$ 30 |
Location: |
ENAGA North & West field development Libya area NC 177 |
Scope of work: |
Pre commissioning, commissioning and start up of the CPF |